Capital Projects

The Township current has the following engineering capital projects underway.

Facilities

Project ID Description Projected Completion Status
Z4106 FM - Operations Centre - Roof Replacement Q3 2011 Project delayed to May 2012 start

Roads and Transportation

Project ID Description Projected Completion Status
Z4105 RDS - Fraser Hwy at 248 Street - Northbound left turn phase
Z4534 RDS - 0 Ave at 252 Street; Bridge Reconstruction Q3 2012 Project complete except for pavement restoration 
Z4070 RDS - 16 Ave @ 256 St - Left Turn Lane Complete  Project complete
Z4487 RDS - 200 St at 68Th Ave; Ped Overpass Q3 2012 Completing final portion - lighting
Z4675 RDS - 216 St; 48Ave To 50 Ave: Widening Complete  Project Complete
Z2930 RDS - 228 St to 235 St; Fraser Hwy Widening Q4 2013 Finalizing design and commencing property acquisition
Z4012 RDS - 232 St at 56 Ave - Intersection Q3 2012 Construction to begin in April 2012
Z0234 RDS - 272St at 29 Ave; Ped Signal Ins Q3 2012 Project underway
Z3619 RDS - 56Ave & Nicomekl; Bridge Recon Q4 2013 2012 Design and 2013 tender/construction
Z4680 RDS - Commuter Cycling - 200 Street widening and marking Q3 2012 Project is in progress. Lane signage and line marking remains to be completed
Z4654 RDS - Commuter Cycling - 224 St Shoulder Widening Q3 2012 Project is in progress. Lane signage and line marking remains to be completed
Z4105 RDS - Fraser Hwy at 248 St; Intersect Q2 2012 Project is substantially complete
Z4507 RDS - Fraser Hwy Widening: Old Yale to 215 Street Q3 2012 Road widening construction underway
Z4484 RDS - Mavis/Glover Signal Installation Q4 2012 CN Rail is currently completing design work
Z4676 TRN - 201 St; 69 Ave to 74 Ave Traffic Calming Complete Project complete

Stormwater

Project ID

Description

Projected Completion

Status

Z1375 STW - 202B st; 68 Ave To 72 Ave; Stormwater Trunk Complete Project complete
Z4469 STW - 206St at 24 Ave - Replacement Blvd Pipe Complete Project is complete
Z4476 STW - 232 St At 30 Ave - Bank Stabilization Q3 2013 Assessment complete
Z4587 STW - 240 Street, 2600 Block - Culvert Replacement Complete Project complete
Z4478 STW - 24Ave at 264 St; Detention Pond Complete Project complete
Z4586 STW - 43 Avenue, 27300 Block - CSP - 5 Culvert Replacements Complete Project complete  
Z4505 STW - 64 Ave From 260-264 St - Drain Q3 2012 12 culvert replacement - 1 culvert remains outstanding
Z4569 STW - 8400 Block of 196 St - Culvert Replacement Complete Project complete
Z4520 STW - Dyking: West Langley Q2 2012 Project complete
Z4679 STW - Old Yale Rd; 21488-21562 Q2 2012 Project is substantially complete.

Sewer

Project ID Description Projected Completion Status
Z4547 SWR - 203 St N. Of 62 Ave Pump Stn Q3 2012 Construction phase
Z4651 SWR - 203 St; 68 Ave - 64 Ave; Sewer Twinning: Phase 1 Q3 2012 Construction phase
Z4545 SWR - 28B Lift Station Upgrades Q4 2012 Wet well lid replaced.  Design is near completion.  
Z4537 SWR - Fort Langley Sanitary Sewer Diversion Complete Project is complete
Z4501 SWR - Sewer Forcemain / Twinning (GVS&DD) Q3 2012 Construction phase
Z4651 SWR - Twinning 200 St 58-56 Ave Q3 2012 Construction phase

Water

Project ID Description Projected Completion Status
Z4494 WTR - 208 St , 80 Ave to 84 Ave - Watermain replacement Complete Project complete
Z4388 WTR - Forest Knolls Watermain Replacement Phase II Q2 2012 Construction nearing completion
Z0635 East Langley Water Supply 2014 On July 12, 2011, Township of Langley Council endorsed the 52 Avenue alignment for the East Langley Water supply.
East Langley Water Supply FAQ’s
Council Report: en10-111 East Langley Water