Facilities
|
| Project ID |
Description |
Projected Completion |
Status |
| Z4106 |
FM - Operations Centre - Roof Replacement |
Q3 2011 |
Project delayed to May 2012 start |
Roads and Transportation
|
| Project ID |
Description |
Projected Completion |
Status |
| Z4105 |
RDS - Fraser Hwy at 248 Street - Northbound left turn phase |
|
|
| Z4534 |
RDS - 0 Ave at 252 Street; Bridge Reconstruction |
Q3 2012 |
Project complete except for pavement restoration |
| Z4070 |
RDS - 16 Ave @ 256 St - Left Turn Lane |
Complete |
Project complete |
| Z4487 |
RDS - 200 St at 68Th Ave; Ped Overpass |
Q3 2012 |
Completing final portion - lighting |
| Z4675 |
RDS - 216 St; 48Ave To 50 Ave: Widening |
Complete |
Project Complete |
| Z2930 |
RDS - 228 St to 235 St; Fraser Hwy Widening |
Q4 2013 |
Finalizing design and commencing property acquisition |
| Z4012 |
RDS - 232 St at 56 Ave - Intersection |
Q3 2012 |
Construction to begin in April 2012 |
| Z0234 |
RDS - 272St at 29 Ave; Ped Signal Ins |
Q3 2012 |
Project underway |
|
|
|
|
| Z3619 |
RDS - 56Ave & Nicomekl; Bridge Recon |
Q4 2013 |
2012 Design and 2013 tender/construction |
| Z4680 |
RDS - Commuter Cycling - 200 Street widening and marking |
Q3 2012 |
Project is in progress. Lane signage and line marking remains to be completed |
| Z4654 |
RDS - Commuter Cycling - 224 St Shoulder Widening |
Q3 2012 |
Project is in progress. Lane signage and line marking remains to be completed |
| Z4105 |
RDS - Fraser Hwy at 248 St; Intersect |
Q2 2012 |
Project is substantially complete |
| Z4507 |
RDS - Fraser Hwy Widening: Old Yale to 215 Street |
Q3 2012 |
Road widening construction underway |
| Z4484 |
RDS - Mavis/Glover Signal Installation |
Q4 2012 |
CN Rail is currently completing design work |
| Z4676 |
TRN - 201 St; 69 Ave to 74 Ave Traffic Calming |
Complete |
Project complete |
Stormwater
|
|
Project ID
|
Description
|
Projected Completion
|
Status
|
| Z1375 |
STW - 202B st; 68 Ave To 72 Ave; Stormwater Trunk |
Complete |
Project complete |
| Z4469 |
STW - 206St at 24 Ave - Replacement Blvd Pipe |
Complete |
Project is complete |
| Z4476 |
STW - 232 St At 30 Ave - Bank Stabilization |
Q3 2013 |
Assessment complete |
| Z4587 |
STW - 240 Street, 2600 Block - Culvert Replacement |
Complete |
Project complete |
| Z4478 |
STW - 24Ave at 264 St; Detention Pond |
Complete |
Project complete |
| Z4586 |
STW - 43 Avenue, 27300 Block - CSP - 5 Culvert Replacements |
Complete |
Project complete |
| Z4505 |
STW - 64 Ave From 260-264 St - Drain |
Q3 2012 |
12 culvert replacement - 1 culvert remains outstanding |
| Z4569 |
STW - 8400 Block of 196 St - Culvert Replacement |
Complete |
Project complete |
| Z4520 |
STW - Dyking: West Langley |
Q2 2012 |
Project complete |
| Z4679 |
STW - Old Yale Rd; 21488-21562 |
Q2 2012 |
Project is substantially complete. |
Sewer
|
| Project ID |
Description |
Projected Completion |
Status |
| Z4547 |
SWR - 203 St N. Of 62 Ave Pump Stn |
Q3 2012 |
Construction phase |
| Z4651 |
SWR - 203 St; 68 Ave - 64 Ave; Sewer Twinning: Phase 1 |
Q3 2012 |
Construction phase |
|
|
|
|
| Z4545 |
SWR - 28B Lift Station Upgrades |
Q4 2012 |
Wet well lid replaced. Design is near completion. |
| Z4537 |
SWR - Fort Langley Sanitary Sewer Diversion |
Complete |
Project is complete |
| Z4501 |
SWR - Sewer Forcemain / Twinning (GVS&DD) |
Q3 2012 |
Construction phase |
| Z4651 |
SWR - Twinning 200 St 58-56 Ave |
Q3 2012 |
Construction phase |
Water
|
| Project ID |
Description |
Projected Completion |
Status |
| Z4494 |
WTR - 208 St , 80 Ave to 84 Ave - Watermain replacement |
Complete |
Project complete |
| Z4388 |
WTR - Forest Knolls Watermain Replacement Phase II |
Q2 2012 |
Construction nearing completion |
| Z0635 |
East Langley Water Supply |
2014 |
On July 12, 2011, Township of Langley Council endorsed the 52 Avenue alignment for the East Langley Water supply.
East Langley Water Supply FAQ’s
Council Report: en10-111 East Langley Water |