Highway 1 - 216 Street to 264 Street Widening Project

The Highway 1 widening project between 216 and 264 Streets is underway. The following impacts are anticipated:

  • May 13 and 14: The left lane of Highway 1 eastbound at 232 Street will close to traffic on Thursday, May 13 from 3:30 to 5:30am, and again from 9:00pm until 5:30am the next morning.
  • April 22  through end of June: Construction of a structural test pile, located in the median of Highway 1 on the east side of the 232 Street underpass. This work will aid in determining the adequate foundation capacity required for the new 232 Street underpass structure. Construction is scheduled to commence on April 22, 2021 and will be restricted to the hours of 7:00am and 7:00pm, Monday through Friday, and 9:00am to 5:00pm on Saturdays. No work is permitted on Sundays. This construction is anticipated to be completed by the end of June.

Information on the overall project can be found on the BC Government website.  If further information is required about the project, please email 216to264.Widening@gov.bc.ca